Development

Posted about 1 month ago

Edyb_bent_2_6-16-10_001

Bridge Construction Put On-Hold

 

Bridge construction on ODOT’s $215 million U.S. 20:  Pioneer Mountain-Eddyville project in Lincoln County has been delayed so that engineers can reconsider calculations related to how much sub-surface ground pressure is being exerted on bridge components.

 

The Design Builder’s original calculations have been in question since columns at two bridge locations tilted out-of-plumb.  The movement of the columns was discovered during a routine survey in February.   

 

The design engineering firm, URS Corporation, working as a sub-contractor to the project’s Design Build contractor, Yaquina River Constructors, has determined that it needs to monitor ground forces at four bridge locations while its engineers reanalyze their original calculations.

 

The delay in construction will mean a delay of project completion but it remains uncertain at this time how long the delay might be.

Other Construction Continues

 

The delay of bridge construction does not mean a complete halt to construction of other aspects of the project.

 

Still underway is:

  • The new alignment’s eastern and western intersections with the existing U.S. 20 will be complete this summer, meaning no more 20 minute delays while other construction continues;
  • The remaining 920,000 cubic yards of excavation work;
  • All remaining culvert and stormwater system work;
  • Revegetation with native plants and seed mixes of the disturbed areas; and
  • Paving will be completed on about 2.5 miles of the new alignment.

Project to enhance travel and safety on U.S. 20 corridor

 

The project is building a six-and-a-half mile section of new road that bypasses a ten mile stretch of substandard highway with no passing opportunities and many curves where the speed limit is 35 miles-per-hour.  The new road will have wider travel lanes and shoulders, and will create miles of passing lanes.

 

A significant part of the project is the construction of ten bridges along the new alignment.  All but four bridges are essentially complete. 

 

The four bridges where construction has been delayed are:

  • Cougar Creek Bridge- A 600 foot long structure that spans Cougar Creek
  • Crystal Creek Bridge- A 1,100 foot long structure that spans Crystal Creek
  • Eddy B Bridge- A 750 foot long structure  that spans Eddy Creek Tributary B
  • Eddy C Bridge- A 600 foot long structure that spans Eddy Creek Tributary C

 Bents, (the vertical support columns) have moved at only two bridge locations-- Cougar Creek and Eddy B--but because the Design Builder’s engineers are modifying their design parameters related to soil strength across the project site, construction may be delayed at these four critical bridges until they do more subsurface monitoring to confirm their design assumptions.

 

Project Background

 

The U.S. 20:  Pioneer Mountain-Eddyville project broke ground in December, 2005.

 

Work was halted in July, 2007 after the discovery of ancient, massive landslides changed the scope of the project.

 

Work resumed in May, 2008 after Yaquina River Constructors and ODOT agreed on how the effects of landslides would be mitigated in construction. 

 

Mitigation included construction of:

 

  • Buttresses-In simple words, a buttress is a man-made mound or hill of soil or rock placed at the toe of the slope. The buttress increases the resisting forces and thus prevents material from moving towards the toe of the slope. 
  • Shear-keys-In simple words, a shear-key is a trench excavated into the stable soil so that the new fill placed over the natural slope firmly keys into the existing soil.

What happens next?

 

Engineers will now determine if landslide areas are continuing to move and if the ability of bridge components to withstand the earth pressure has been miscalculated.

 

If the construction methods have not stopped the slides, the Design Builder and their engineers and ODOT will determine how best to proceed.   Options include:

  • Constructing new buttress and shear-key configurations
  • Readdressing the amount of fill material placed in some locations
  • Creating longer bridge spans to replace bridge abutment fill material
  • Consider different bridge construction techniques

Second U.S. 20 project NOT affected

 

Meantime, work on the U.S. 20:  Pioneer Mountain Loop Road-Yaquina River project, immediately west of Pioneer Mountain-Eddyville, continues on schedule.

 

The $8.5 million project will realign the curves near Sam’s Creek Road.  The highway will be shifted north for environmental protection of the creek and will construct a new, fish-friendly bridge over Simpson Creek, replacing a restrictive culvert.

News Release

Posted about 1 month ago

06_132_r2_pme_bridge_construction_delay

The February discovery of movement of two bridge bents has necessitated new steps. Click on the document to read a current news release.

Detour Map

Posted 3 months ago

Pme_detour_map_final

Small construction blasts will continue near the area of US 20 between mileposts 23 and 25.  During these blasts, there is always the potential for debris to force a temporary closure of US 20 at that location.  We always provide advance word to the news media, employers and other stakeholders.  Should temporary closures be necessary, it's a good idea to know what alternate routes are available.  Click on the adjacent map to learn more.

Big Beams

Posted 5 months ago

Pme_beams_011

More than 100 giant, precast concrete beams, to be used in bridge construction,  will be delivered to the US20-Pioneer Mountain to Eddyville project beginning Thursday, February 25.

 

The beams will be trucked from Harrisburg, along OR99E to OR34/US 20, and then west to the project site near Eddyville.

 

The beams measure 150-feet long and weigh approximately 67 tons each.  Four beams will be delivered February 25.    The remaining beams will be delivered from March through early June.  No deliveries will be made during weekends.  The beams will be trucked by 12-axle trucks that are steered in front and back.

 

“Motorists may experience a minor delay by the oversize loads,” said Assistant Project Manager Eric Knapp.  “Those big beams will be taking turns and intersections a little more slowly than some motorists travel,” he said.

 

The beams were manufactured by Knife River Corporation, Northwest at their Prestress Concrete Division plant in Harrisburg.  Each beam takes a day to fabricate and Knife River is supplying 188 beams for the bridges in the project.

 

“The beams represent added value for Oregon taxpayers on a couple of levels,” said Knapp.  “First, they’re made by Oregon workers.  Secondly, they’re designed to be interchangeable.  All the beams used for bridge construction in this project are built to the same specifications.  That saves taxpayers a lot of money in design costs,” Knapp said.

Update

Posted 5 months ago

During the past few weeks, much has been accomplished on the project.

  • Fill 8 and Fill 10 settlement periods have progressed.
  • Work on erosion and sediment control continues.

Bridge construction continues to progress.

  • Eddy C Bridge--Substructure work is complete; beam placement will occur in March.  Beams are scheduled to be delivered February 26.
  • Eddy B Bridge--Substructure work is complete; beam placement will be scheduled soon.
  • Crystal Creek Bridge--Cross-beam construction has begun.
  • Cougar Creek Bridge--The substructure is nearly complete. 
  • Trapp Creek Bridge--Forms are being stripped.  Rail and end panel construction is in progress.