Update
Posted February 12, 2010
During the past few weeks, much has been accomplished on the project.
- Fill 8 and Fill 10 settlement periods have progressed.
- Work on erosion and sediment control continues.
Bridge construction continues to progress.
- Eddy C Bridge--Substructure work is complete; beam placement will occur in March. Beams are scheduled to be delivered February 26.
- Eddy B Bridge--Substructure work is complete; beam placement will be scheduled soon.
- Crystal Creek Bridge--Cross-beam construction has begun.
- Cougar Creek Bridge--The substructure is nearly complete.
- Trapp Creek Bridge--Forms are being stripped. Rail and end panel construction is in progress.