Development

Posted June 17, 2010

Edyb_bent_2_6-16-10_001

Bridge Construction Put On-Hold

 

Bridge construction on ODOT’s $215 million U.S. 20:  Pioneer Mountain-Eddyville project in Lincoln County has been delayed so that engineers can reconsider calculations related to how much sub-surface ground pressure is being exerted on bridge components.

 

The Design Builder’s original calculations have been in question since columns at two bridge locations tilted out-of-plumb.  The movement of the columns was discovered during a routine survey in February.   

 

The design engineering firm, URS Corporation, working as a sub-contractor to the project’s Design Build contractor, Yaquina River Constructors, has determined that it needs to monitor ground forces at four bridge locations while its engineers reanalyze their original calculations.

 

The delay in construction will mean a delay of project completion but it remains uncertain at this time how long the delay might be.

Other Construction Continues

 

The delay of bridge construction does not mean a complete halt to construction of other aspects of the project.

 

Still underway is:

Project to enhance travel and safety on U.S. 20 corridor

 

The project is building a six-and-a-half mile section of new road that bypasses a ten mile stretch of substandard highway with no passing opportunities and many curves where the speed limit is 35 miles-per-hour.  The new road will have wider travel lanes and shoulders, and will create miles of passing lanes.

 

A significant part of the project is the construction of ten bridges along the new alignment.  All but four bridges are essentially complete. 

 

The four bridges where construction has been delayed are:

 Bents, (the vertical support columns) have moved at only two bridge locations-- Cougar Creek and Eddy B--but because the Design Builder’s engineers are modifying their design parameters related to soil strength across the project site, construction may be delayed at these four critical bridges until they do more subsurface monitoring to confirm their design assumptions.

 

Project Background

 

The U.S. 20:  Pioneer Mountain-Eddyville project broke ground in December, 2005.

 

Work was halted in July, 2007 after the discovery of ancient, massive landslides changed the scope of the project.

 

Work resumed in May, 2008 after Yaquina River Constructors and ODOT agreed on how the effects of landslides would be mitigated in construction. 

 

Mitigation included construction of:

 

What happens next?

 

Engineers will now determine if landslide areas are continuing to move and if the ability of bridge components to withstand the earth pressure has been miscalculated.

 

If the construction methods have not stopped the slides, the Design Builder and their engineers and ODOT will determine how best to proceed.   Options include:

Second U.S. 20 project NOT affected

 

Meantime, work on the U.S. 20:  Pioneer Mountain Loop Road-Yaquina River project, immediately west of Pioneer Mountain-Eddyville, continues on schedule.

 

The $8.5 million project will realign the curves near Sam’s Creek Road.  The highway will be shifted north for environmental protection of the creek and will construct a new, fish-friendly bridge over Simpson Creek, replacing a restrictive culvert.